For all residents affected by the proposed closure of Seven Hills Road, Cobham, Surrey by Souther Gas Networks.
I have just been informed of the following by Souther Gas Networks
UPDATE: We have worked closely with Surrey County Council and have listened to the concerns of residents and road users regarding this project. As a result, a revised programme of work has been planned, including closures of Seven Hills Road for certain periods during the Christmas/New Year, Easter and summer holidays. Additional work will take place outside these dates but will not result in road closures.
The outline of the planned programme of work, which will begin on 28th December, is shown below.
28/12/09 – 03/01/10: Seven Hills Road closed and lane restrictions on Byfleet Road. Seven Hills Road will reopen on 04/01/10
04/01/10 – 31/01/10: Lane restrictions in Seven Hills Road South
15/03/10 – 11/04/10: Lane restrictions on Queens Road Roundabout
29/03/10 – 11/04/10: Seven Hills Road closed. The road will reopen on 12/04/10
20/06/10 – 29/08/10: Seven Hills Road closed. The road will reopen on 30/08/10
While we realise that our work will still cause disruption, we are working hard to try and minimise this and will make every effort to complete this project as soon as we can.
During the closures of Seven Hills Road, through traffic will need to use a diversionary route via Queens Road, Esher Bypass, Copsem Lane and the A3 and vice versa. Access to residents, businesses and the school in Seven Hills Road will be maintained throughout and we will be working seven days a week and extended hours where it is safe and possible to do so.